Politics1 min read

Texas resumes issuing data center air permits, regulator says

By · Published by Everything Blog

In short

The Texas Commission on Environmental Quality confirmed it has restored the standard review framework for server facility air permits governed by state and federal laws. Republican Governor Greg Abbott had previously paused both grid connections and environmental approvals to assess local community, ecological, and power grid impacts. This reversal arrives just before Democrat Gina Hinojosa assumes the governorship in January with plans to halt future developments. Analysts warn the eleventh-hour approvals will likely alienate incoming state lawmakers and eliminate chances for an early compromise with the tech sector.

Key points

  • Incoming Democratic Governor Gina Hinojosa has committed to imposing a moratorium on data…: Incoming Democratic Governor Gina Hinojosa has committed to imposing a moratorium on data center construction upon entering office.
  • Resuming regulatory approvals risks triggering intense political pushback from newly elec…: Resuming regulatory approvals risks triggering intense political pushback from newly elected Democratic lawmakers in the upcoming legislative cycle.
  • Market analysts at TD Cowen caution that this late policy reversal diminishes opportuniti…: Market analysts at TD Cowen caution that this late policy reversal diminishes opportunities for compromise between developers and the incoming administration.

Sources checked by our analysis pipeline: 1

NEW YORK, Nov 18 : Texas has resumed issuing air permits for data centers, state regulators said on Wednesday, after pausing the practice last month as part of the state's broader attempt to manage the server warehouses and their effects on the electrical grid, communities and the environment.

• The Texas Commission on Environmental Quality "has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said.

• Texas Governor Greg Abbott halted the connection of new data centers to the state electric grid in August and ordered an audit of the projects, rattling one of the world's fastest-growing hubs for data center development. Abbott followed up by temporarily blocking air permits for all data center projects.

• The air permit resumption came after the Texas grid operator notified the TCEQ that it had collected "community impact review" information for proposed data center projects, Lopez said.

• Abbott, a Republican, lost his reelection bid in this month's midterm elections to Democratic challenger Gina Hinojosa, who has promised…

Politics