Noida couple's Rs 64L home loan stalls; forum orders flat handover

By · Via Times of India · Published by Everything Blog

In short

Homebuyers Manoj Kumar Bhrigu and Niranjana Sharma had booked a 1,595-square-foot flat for Rs 77,35,575 and paid an initial deposit of Rs 7.5 lakh. The remaining balance was stalled when the builder failed to furnish two critical documents required by the Central Bank of India to disburse an approved Rs 64 lakh home loan. JSS Buildcon then cited non-payment to unilaterally cancel the booking, but the commission deemed this move a deficiency in service. The forum ordered the developer and its directors to execute the flat handover within 30 days of receiving the balance and pay litigation costs.

Key points

  • Real estate builders cannot penalize buyers for payment delays directly caused by the fir…: Real estate builders cannot penalize buyers for payment delays directly caused by the firm's failure to supply bank documentation.
  • The consumer disputes forum classified the developer's unilateral allotment cancellation…: The consumer disputes forum classified the developer's unilateral allotment cancellation as a deficiency in service and an unfair trade practice.
  • The company and its directors face mandatory property transfer obligations alongside a Rs…: The company and its directors face mandatory property transfer obligations alongside a Rs 5,000 litigation penalty following the ex parte order.

Sources checked by our analysis pipeline: 1

NOIDA: A couple residing in Sector 74, who were denied possession of a flat after a builder cancelled their allotment over alleged non-payment, have been granted relief. The district consumer disputes redressal commission has directed the company and its two directors to hand over the apartment within 30 days of receiving the balance payment in accordance with the builder-buyer agreement.

The commission also directed the opposite parties to pay Rs 5,000 towards litigation costs. The order was passed ex parte on Nov 7 by the commission's president, Anil Kumar Pundir, and member Anju Sharma, after the company and its directors failed to respond to the complaint or participate in the proceedings.

The complaint was filed on June 22, 2024, by Manoj Kumar Bhrigu and his wife, Niranjana Sharma, residents of Grand Ajnara Heritage in Sector 74.

They had booked a 1,595 sq ft flat in a project by JSS Buildcon Pvt Ltd for Rs 77,35,575.

According to the complaint, the couple paid Rs 1 lakh by cheque on July 7, 2023, and another Rs 6.5 lakh on July 28, 2023,…