Man wins Rs 1.26 crore from consumer court after builder fails to deliver his flat

By · Via Times of India · Published by Everything Blog

In short

Homebuyer Pratap Premchand Agarwal originally booked a flat in the Enrico Heights project in November 2011 with an agreed completion target of October 2015. Possession was only offered in July 2019, but the unit was incomplete, uninhabitable, and lacked statutory completion or occupation certificates. Although Universal Drinks Pvt Ltd claimed it settled Agarwal's Rs 1.31 crore loan with Canara Bank, the commission ruled this fulfilled a tripartite agreement rather than compensating the buyer. The developer must now reimburse the homebuyer's direct payments alongside litigation costs within eight weeks.

Key points

  • Settling a buyer's bank loan under a tripartite pact does not clear a developer's duty to…: Settling a buyer's bank loan under a tripartite pact does not clear a developer's duty to refund the buyer's personal funds.
  • Developers offering delayed possession without statutory completion or occupation certifi…: Developers offering delayed possession without statutory completion or occupation certificates remain liable for full refunds.
  • Failure to pay the refund within eight weeks will escalate the developer's annual interes…: Failure to pay the refund within eight weeks will escalate the developer's annual interest penalty from 9 percent to 12 percent.

Sources checked by our analysis pipeline: 1

NEW DELHI: The national consumer commission has directed a Nagpur-based real estate developer to refund over Rs 1.26 crore to a homebuyer for failing to deliver a flat within the promised period. The commission ordered developer to pay 9 percent annual interest on the refundable amount from the respective dates of payment until realisation.

It also directed the company to pay Rs 1 lakh towards litigation expenses.

In its November 18, 2026, order, the commission said the developer could not escape its liability to refund the money paid by the buyer merely because it had subsequently settled his housing loan with

Canara Bank.

Builder fails to deliver flat despite receiving over Rs 1.82 crore

According to the commission order, Pratap Premchand Agarwal had booked a flat in the Wisteria Tower of the Enrico Heights project in Somalwada, Nagpur, on November 21, 2011, by paying Rs 11 lakh.

An allotment confirmation was executed on September 20, 2012, for the 2,573 sq ft flat, with two parking slots, at a total consideration of Rs 1,70,74,500. After receiving Rs 60,00,350, the developer executed…