Homebuyer wins Rs 1.36 crore RERA refund as Bombay HC rejects builder's plea

By · Via Times of India · Published by Everything Blog

In short

The developer contested a 2019 Maharashtra Real Estate Regulatory Authority directive and a 2021 recovery order, arguing that an adjudicating officer lacked the jurisdiction to grant refunds under a later Supreme Court interpretation. However, the High Court clarified that delegating refund powers under Section 81 of RERA is not prohibited by that precedent. Emphasizing statutory deadlines, the bench held that settled disputes cannot be revived simply because subsequent rulings interpret the law differently. As a result, the flat purchaser will recover approximately Rs 1.36 crore alongside 10.20% annual interest.

Key points

  • Belated legal challenges will be rejected when parties fail to appeal regulatory orders w…: Belated legal challenges will be rejected when parties fail to appeal regulatory orders within the prescribed statutory timeframe.
  • The High Court determined that RERA provisions permit delegating refund powers to an adju…: The High Court determined that RERA provisions permit delegating refund powers to an adjudicating officer under Section 81.
  • Past closed and settled legal matters cannot be reopened merely due to newer interpretati…: Past closed and settled legal matters cannot be reopened merely due to newer interpretations issued by superior courts.

Sources checked by our analysis pipeline: 1

You buy a flat and due to some dispute with the real estate developer, you seek a refund and the Real Estate Regulation Authority (RERA)’s adjudicating officer passes an order in your favour. Years later, the developer challenges the order on the basis of a fresh Supreme Court ruling. What happens then?

The Bombay High Court has dismissed a petition filed by a real estate developer which sought to set aside an order directing it to refund Rs 1.36 crore, along with interest at 10.20% per annum, to a flat purchaser.

The developer argued that a subsequent Supreme Court ruling had rendered the original refund order legally invalid.

The Bombay High Court rejected the developer’s plea and declined to reopen an order that had attained finality after the developer failed to challenge it within the prescribed statutory period. Read on to know what happened.

What the case is about

The dispute arose from an order in 2019, passed by an adjudicating officer of the Maharashtra Real Estate Regulatory Authority. The officer had directed the real estate developer to refund Rs…