The 2.5-kilometer elevated corridor was initially planned to finish in November 2019, but it faced termination of its original builder following judicial intervention and financial troubles. Current contractor BSCPL Infrastructure Ltd has encountered fresh difficulties, including casting yard issues and a mandatory Indian Institute of Science structural assessment completed in May 2024. Execution remains hampered by pending land acquisition near St John's Medical College Hospital and citizen opposition to felling 157 trees on Koramangala's 100 Feet Road.
Key points
Contractor transitions and official penalties have failed to accelerate the corridor past…: Contractor transitions and official penalties have failed to accelerate the corridor past its persistent scheduling setbacks.
Unresolved land acquisition issues near major healthcare facilities continue to prevent t…: Unresolved land acquisition issues near major healthcare facilities continue to prevent the project's physical completion.
Significant environmental opposition and structural reassessments have substantially expa…: Significant environmental opposition and structural reassessments have substantially expanded the infrastructure corridor's original timeline and budget.
Sources checked by our analysis pipeline: 1
BENGALURU: Bengaluru's much-delayed Ejipura flyover, dubbed the city's 'Stonehenge' for its years of stalled construction and unfinished pillars, is staring at yet another deadline miss.
Nearly nine years after work began, the 2.5km elevated corridor may not be ready even by December-end, prolonging commuters' wait for relief along the busy Koramangala–Ejipura–Madiwala stretch.
Originally scheduled for completion in November 2019, the project has endured repeated deadline extensions, contractor failure, failed tenders, land acquisition hurdles, delayed clearances and disputes over payments.
Despite a change of contractor and several assurances from civic authorities, the flyover remains unfinished.
From 2017 to 2022: Simplex fails to complete the project
The flyover was originally awarded to Kolkata-based Simplex Infrastructure Ltd in 2017, with an estimated project cost of Rs 158 crore. BBMP issued the work order on May 4, 2017, and the project was scheduled for completion by November 2019.
However, construction faced problems from the beginning. Delays in traffic police clearances, permission for controlled blasting and land acquisition affected the pace of work.
By 2020, BBMP was still struggling to acquire portions of land required…
Sandra Thomas and her husband Philip abused their positions under a lasting power of attorney by liquidating elderly mother Jeanne MacDougall's assets to finance lavish lifestyle expenditures. The High Court determined the pair exerted undue influence, stripping the late matriarch of virtually all cash reserves prior to her 2020 death without planning for her long-term care needs. Although the court mandated extensive asset recovery, it upheld the mother's 2011 will against a challenge from her son.
Medical experts told a regional coroner that critical risks made the home delivery unsuitable, including gestation past 41 weeks and the potential need for rapid surgical interventions. The primary midwife chose to remain present because of grave concerns that the mother would otherwise undertake an entirely unassisted free birth. The broader probe focuses on four infant fatalities across the state's northern rivers region linked to alternative delivery settings.
European Union regulators have granted formal market authorization to the pharmaceutical company for its updated immunization against rabies. This regulatory clearance permits the rollout of the preventive treatment across member nations to address the viral threat. The decision represents a key advancement in the company's regional portfolio for infectious disease protection.