The Land Transport Authority reported that systemwide rail performance retreated from its all-time high, driven primarily by operational hiccups on the orbital route alongside a small slide on the Downtown Line. Meanwhile, the North-South and North East lines managed slight reliability gains, and the East-West Line held completely steady. In contrast to the heavy rail system, the light rail network experienced substantial improvements following long-term infrastructure renewal projects. All monthly figures remain provisional pending final incident investigations by the transport regulator.

Key points

  • Commuters experienced zero major train delays exceeding 30 minutes across the mature netw…: Commuters experienced zero major train delays exceeding 30 minutes across the mature network during October.
  • The MRT network maintained its performance above the critical two million train-km thresh…: The MRT network maintained its performance above the critical two million train-km threshold for seven consecutive months.
  • Extensive renewal works on the LRT system have begun delivering measurable, double-digit…: Extensive renewal works on the LRT system have begun delivering measurable, double-digit reliability gains for suburban commuters.

Sources checked by our analysis pipeline: 1

The overall MRT network's 12-month mean kilometres between failure fell 7 per cent to 3.14 million train-km, but remained above 2 million train-km for a seventh consecutive month.

SINGAPORE: The Circle Line's mean kilometres between failure (MKBF) fell 23 per cent in October, according to the Land Transport Authority's (LTA) latest rail reliability report published on Thursday (Nov 19).

Singapore tracks the reliability of its MRT network using mean kilometres between failure (MKBF) - the average distance travelled by trains before a delay of more than five minutes.

The monthly MKBF figures are based on a 12-month moving average, with the October figure covering the period from November 2025 to October 2026.

LTA said the October figures are provisional and subject to adjustment pending ongoing incident investigations.

The MKBF for the Circle Line fell to 1.97 million train-km in October, down from 2.57 million in September.

However, the Circle Line's train service delivery improved to 99.85 per cent from 99.79 per cent, while train punctuality was unchanged at 99.31 per cent.

LTA's report showed there were no Circle Line service…