Six family members invested over Rs 1.9 crore between December 2023 and January 2024 to open a commercial cloth outlet. The builder executed an agreement promising possession by February 2029 alongside assured returns, but stopped making the payouts after June 2024. After learning that construction had halted and the project's RERA registration had lapsed, the family rejected an offer to transfer funds to another site and pursued legal action. The commission ordered the developer to pay Rs 1,96,75,547 with 12% interest within 30 days, plus Rs 75,000 for harassment.

Key points

  • Buyers are legally justified in seeking early refunds when builders stall construction an…: Buyers are legally justified in seeking early refunds when builders stall construction and fail to maintain valid RERA registrations.
  • Commercial property purchasers can qualify as consumers under the law if the investment i…: Commercial property purchasers can qualify as consumers under the law if the investment is intended for self-employment.
  • The ruling mandates additional financial penalties, including Rs 75,000 in compensation f…: The ruling mandates additional financial penalties, including Rs 75,000 in compensation for mental agony caused by the developer.

Sources checked by our analysis pipeline: 1

CHANDIGARH: For a family that pooled nearly Rs 2 crore to set up a cloth retail business, the promise of owning commercial space in a project in Zirakpur gradually turned into a prolonged wait, unpaid assured returns and growing uncertainty. The State Consumer Disputes Redressal Commission, Chandigarh, has directed the developer to refund Rs 1.96 crore with 12% annual interest.

The case began when six family members jointly purchased a commercial unit. Between Dec 17, 2023, and Jan 12, 2024, they paid a total of Rs 1.9 crore. They told the commission that they intended to establish and operate a cloth retail outlet.

An allotment letter and an agreement to sell were executed on Feb 6, 2024. The agreement stipulated that possession would be handed over by Feb 6, 2029. Although the agreement set Feb 6, 2029, as the possession deadline, the family alleged that the developer had initially promised delivery within three years. A day after the agreement was signed, the parties entered into an MoU providing for assured returns.

The family received Rs 2.2 lakh, after TDS deduction,…