Adani project work on at village not listed in clearance: Official

By · Via Times of India · Published by Everything Blog

In short

The Maharashtra Pollution Control Board launched an inquiry into Adani Green Energy Ltd after receiving complaints about excavation work in Satara's Sawarghar village for the 1,500MW Tarali project. While an honorary wildlife warden pointed out that Sawarghar was excluded from the federal environmental clearance, the company stated it purchased private land for a worker camp sanctioned by the Central Electricity Authority. Regulators have already observed land-leveling at the site and are preparing an official inspection report. Furthermore, this review follows an unheeded forest department stop-work order tied to missing wildlife board clearances.

Key points

  • The corporate developer risks potential legal action and regulatory pushback over missing…: The corporate developer risks potential legal action and regulatory pushback over missing wildlife permits in an ecologically sensitive zone.
  • Adani Group defends its operations by claiming private land purchases for worker housing…: Adani Group defends its operations by claiming private land purchases for worker housing were covered by Central Electricity Authority layout approvals.
  • State pollution control authorities plan to forward their on-site inspection findings to…: State pollution control authorities plan to forward their on-site inspection findings to higher officials for formal review and potential action.

Sources checked by our analysis pipeline: 1

MUMBAI: Amid a row over work on Adani Green Energy Ltd’s (AGEL) 1,500MW Tarali pumped storage project beginning in Satara’s Patan taluka despite lack of approval from National Board for Wildlife (NBWL), the state forest department’s honorary wildlife warden for the district has written to Maharashtra Pollution Control Board (MPCB) alleging that large-scale excavation and construction is underway in Sawarghar village, which was not listed on the environmental clearance (EC) granted by the Union forest ministry on Feb 11 last year.

The honorary wildlife warden, Rohan Bhate, said the EC specified only four villages that stand to be affected—Nivade, Tondoshi, Kalambe and Jalu—in the district.

A spokesperson from Adani Group said the EC covers the four villages as well as Dafalwadi, and the company later purchased private land in Sawarghar to set up temporary accommodation for workers. The company said such an accommodation was included in the project layout approval from Central Electricity Authority. It said the project has all the relevant clearances and initial works are in progress at the site.

The Tarali project, estimated at Rs 5,675 crore,…